The stages, and what happens in each
Discussion and quotation. Floor plan, brief, budget, an initial figure. Fast — days, not weeks, provided you know your budget range.
Site measurement. A half-day visit. Everything afterwards is drawn to your actual walls rather than the builder's drawing.
Design and 3D. The longest creative stage, and the one worth taking time over. You see materials, light and proportion before anything is cut.
Iteration and freeze. Changes here are free. Changes after this stage are not.
Production. Boards cut and machined, custom pieces fabricated, materials ordered. Long-lead items — a specific stone slab, an imported light fitting — are ordered now or they become the critical path.
Installation. Sequenced on site: civil, ceiling, electrical, joinery, finishes. Overlapping trades badly is what turns a clean project into a slow one.
Snagging and handover. Punch list, adjustments, cleaning.
What actually causes delays
Changes after the design freeze. By a distance the most common cause. A wardrobe moved after its panels are cut is not an edit; it is a re-manufacture.
Long-lead materials ordered late. Decorative lighting, specific stone slabs and imported hardware can run four to eight weeks. These must be decided at design stage, not at installation.
Site not ready. Builder snags outstanding, water or power not connected, lift not commissioned.
Society restrictions. Working hours, weekend bans, lift booking, debris removal windows. Ask your association for the rules in writing before the schedule is drawn.
Payment stages missed. Production is released against stage payments; a delayed payment delays a factory slot, and slots are not held.
What you can do to protect the schedule
Freeze the design completely — every material, every finish, every handle — before production starts. Decide the decorative lighting early. Get the society rules in writing. Keep one decision-maker in the household rather than three. And resist the urge to add a small extra unit in month two; it is never small once it is in the sequence.
A word on promised timelines
Treat any timeline quoted before a site measurement as an estimate of intent rather than a schedule. A real schedule is issued at the start of production, when the drawings are frozen and the material list is fixed. Ask for it in writing at that point, with stage dates rather than a single end date.